Project context
High-voltage substation construction requiring day-to-day coordination of contractors, engineers and site personnel across civil and electrical work fronts.
Leadership and management oversight
Management responsibilities included leading day-to-day construction coordination, site briefings and progress meetings. The scope also covered oversight of contractor interfaces, work-pack information, inspections and upcoming activities, with reporting on programme, resources, safety, quality and decisions requiring stakeholder input.
Management responsibilities
The responsibilities are summarised below.
- Coordinated concurrent civil and electrical work fronts and contractor interfaces
- Reviewed work packs, risk assessments, method statements and inspection requirements within the appointment
- Led site briefings, coordination meetings and progress reporting
- Coordinated construction-to-commissioning interfaces and completion information